BP To Achieve Full Production At Its Tangguh LNG Plant In Papua, Indonesia
Published: 11-Oct-2009
BP Plc (BP) said that its Tangguh liquefied natural gas (LNG) project will achieve full production this month following a complete shutdown at the plant in August 2009, the Jakarta Globe reported. The company has faced delays at the plant since the 7.6 million ton-a-year operation started production in July 2009. Both of the plant’s processing units, or trains, were closed in August 2009 and September 2009 to resolve technical problems.
“Train 2 has been producing LNG since October 2 and Train 1 started on September 25, with full production expected to commence this month,” Nico Kanter, BP’s Indonesia country head said.
“Tangguh has encountered initial problems but these have been promptly repaired,” Nico said.
BP's Chief Executive, Tony Hayward said of Tangguh, “We have been taking a more relaxed approach to commissioning than we otherwise might have done, given the very depressed market.”
BP is expected to export its fourth shipment of 150,000 metric tons of LNG to China National Offshore Oil Corporation’s terminal in Fujian area sometime next week, Raden Priyono, head of upstream oil and gas regulator BPMigas, said.
“BP is on track to deliver on its commitments for the remainder of the year,” Nico said.
The $5 billion Tangguh plant, situated in Papua’s Bintuni Bay, holds 14.4 trillion cubic feet of proven gas reserves.
BP's Indonesian unit owns 37% of the project. Its partners in the project include Mitsubishi Corporation, Nippon Oil Corporation and Sumitomo Corporation, as well as CNOOC Limited and Talisman Energy Inc.
Network Sites

Suppliers To This Sector
Browse A-Z
RPI
Energy Industry Research ...
CWC School for Energy
Energy Training Courses ...
Parker Filtration and Separation
Compressed Air Treatment and Sample Filtration ...
ATI Stellram
High-Performance Metal Cutting Tools ...
Royal Academy of Engineering
Britain's National Academy for Engineering ...
CEPMLP
Centre for Energy, Petroleum & Mineral Law & Policy ...
White Papers
Browse A-Z
2.5MW Wind Turbine
The latest evolution of GE Energy’s wind turbine technology, the 2.5xl wind turbine, is pl ...
Hardcore® Technology Drilling Solutions for the Heat Exchanger Industry
ATI Stellram develops and produces high-performance metal cutting tools for difficult-to-m ...
Annual Report 2008
IBERDROLA Engineering and Construction has extensive experience in this field, acquired as ...
Increasing Cost-Efficiency of Substation Automation Systems by Centralised Protection Functions
New legislative and customer-oriented requirements pose challenges to substation automatio ...
Applying Modern Communication Technology to Loss-of-Mains Protection
The protection of distribution networks is facing new challenges from an increasing amount ...
Impacts of Quality Improvement Incentives on Automation Investments in the Finnish New Regulation Model
During the second regulatory period of 2008-2011 incentives are included into the Finnish ...


Delicious
Digg
Reddit
Stumble
LinkedIn
Mail sent successfully